On a Schedule

Use On a Schedule for automations such as daily reports, scheduled tasks, or recurring automations.
Note: The On a Schedule event corresponds to the Timer Start Event element in BPMN.


To start the process at a specific time and interval:
  1. Right-click on the Manual Trigger or On App Trigger canvas element.
  2. Select Change Type.
  3. Choose On a Schedule. This sets the Time Trigger activity on the canvas element.
  4. In the properties panel of the Time Trigger activity, configure when the process should start executing.
Read more details about the Time Trigger activity.